Timeline

Referendum/Building Project

Project Timeline

Core Planning Committee (CPC) includes FEH DESIGN, Kraemer Brothers, District Administrator, Business Manager, Activities Director, Facilities Manager, Principals, School Board Members.

A more detailed version of the timeline is attached as a PDF below. If you are have trouble accessing the PDF, please contact the District Office at 920-478-3633.

Approval Meetings

Duration Date(s)
Approve Target Budget 1 day 3/11/19
GMP Approval (Special Mtg) 1 day 4/30/19
Final Cost Proposal and Approval (Special Mtg) 1 day 6/17/19

Construction

Site Construction 320 days 6/3/19-8/21/20
Fitness Addition 105 days 610/19 - 11/1/19
Gymnasium Addition 241 days 6/21/19 - 5/22/20
MEP System and Building Envelope Upgrades 12 wks 6/10/19 - 8/30/19
MEP System and Building Envelope Upgrades 12 wks 6/8/20 - 8/28/20
Bathroom Remodels 12 wks 6/8/20 - 8/28/20