Timeline

Referendum / Building Project

Project Timeline


Core Planning Committee (CPC) includes FEH DESIGN, Kraemer Brothers, District Administrator, Business Manager, Activities Director, Facilities Manager, Principals, School Board Members.

A more detailed version of the timeline is attached as a PDF below. If you are have trouble accessing the PDF, please contact the District Office at 920-478-3633.

Approval Meetings 

Duration 

 Dates

 
 Approve Target Budget  1 day  03/11/19  
 GMP Approval (Special Mtg)  1 day  04/30/19  
 Final Cost Proposal and Approval (Special Mtg)  1 day  06/17/19  

Construction

     
 
Site Construction 
   
  Work to Allow Fitness and Gym Construction 240 days 06/03/19-05/01/20
  High School and New Gym Parking Lot Work 95 days 04/13/20-08/21/20
  New Elementary/Middle School Entrance Work 4 wks  06/15/20-07/10/20
 
 Fitness Addition
120 days  06/10/19-11/22/19 
 
Gymnasium Addition
238 days  07/10/19-06/05/20 
 
MEP System and Building Envelope Upgrades
12 wks 06/08/20-8/28/20 
 
Bathroom Remodels
12 wks  06/08/20-08/28/20 
   
Elementary Bathroom Addition
12 wks  06/08/20-08/28/20 